Contact: Jocelyn Hall, MDOT Office of Communications, 989-245-7117Agency: Transportation
Fast facts:
- MDOT will adjust the truck detour for M-30 following the start of frost law restrictions on Monday, March 1.
- The M-30 temporary bridge has been successfully placed and all deck panels have been installed.
- Following weather delays, crews expect to open the temporary M-30 bridge to traffic on March 12.
February 26, 2021 -- The Michigan Department of Transportation (MDOT) will adjust the posted detour for the M-30 temporary bridge being built in Gladwin County, effective Monday, March 1. The current posted detour directs drivers to use Dale Road as an east/west route crossing the Tobacco River. However, the weight restrictions beginning at 6 a.m. March 1 will prohibit truck traffic from using Dale Road until seasonal weight restrictions are removed. Truck operators should plan to use M-18 to M-61 until further notice. Portable message boards will be placed along those trunklines advising truck traffic of the detour modifications.
More on Michimich.com
Work resumed on the M-30 temporary bridge structure spanning the Tobacco River on Monday, Feb. 15, following paving delays related to low temperatures. Prior to the week-long work stoppage, crews successfully launched the 230-foot prefabricated steel bridge into place. This bridge is the first of its kind used in Michigan and will allow MDOT an opportunity to reopen the M-30 corridor faster than using standard bridge design and construction. When a permanent bridge design is determined, MDOT will remove and store the temporary bridge for use in future projects or emergency road closure situations.
Following the bridge launch in early February, crews placed temporary deck panels finished with an epoxy surface suitable for driving. When hot-mix asphalt (HMA) plants reopen in the spring, crews will return to the site to complete longer-term HMA paving over the roadway.
Despite weather delays, crews are committed to expediting remaining work as quickly and safely as possible and expect to open the M-30 temporary bridge to traffic on Friday, March 12.
Photo: Crews have installed all bridge deck panels. Final paving will be scheduled when plants resume operations in the May.
Fast facts:
- MDOT will adjust the truck detour for M-30 following the start of frost law restrictions on Monday, March 1.
- The M-30 temporary bridge has been successfully placed and all deck panels have been installed.
- Following weather delays, crews expect to open the temporary M-30 bridge to traffic on March 12.
February 26, 2021 -- The Michigan Department of Transportation (MDOT) will adjust the posted detour for the M-30 temporary bridge being built in Gladwin County, effective Monday, March 1. The current posted detour directs drivers to use Dale Road as an east/west route crossing the Tobacco River. However, the weight restrictions beginning at 6 a.m. March 1 will prohibit truck traffic from using Dale Road until seasonal weight restrictions are removed. Truck operators should plan to use M-18 to M-61 until further notice. Portable message boards will be placed along those trunklines advising truck traffic of the detour modifications.
More on Michimich.com
- Pure Michigan Lawn Care Launches Lawn Care and Seasonal Cleanup Services in Howell, MI
- The Inner Power of Emotional Self-Leadership
- Dr. Nadene Rose Shares the Secret to True Success: Faith, Obedience, and Divine Purpose
- Understanding Unexpected Death: Why Independent Autopsies Matter in Cases Without Clear Cause
- Epic Pictures Group Sets North American Release Date for the Thriller NO ORDINARY HEIST
Work resumed on the M-30 temporary bridge structure spanning the Tobacco River on Monday, Feb. 15, following paving delays related to low temperatures. Prior to the week-long work stoppage, crews successfully launched the 230-foot prefabricated steel bridge into place. This bridge is the first of its kind used in Michigan and will allow MDOT an opportunity to reopen the M-30 corridor faster than using standard bridge design and construction. When a permanent bridge design is determined, MDOT will remove and store the temporary bridge for use in future projects or emergency road closure situations.
Following the bridge launch in early February, crews placed temporary deck panels finished with an epoxy surface suitable for driving. When hot-mix asphalt (HMA) plants reopen in the spring, crews will return to the site to complete longer-term HMA paving over the roadway.
Despite weather delays, crews are committed to expediting remaining work as quickly and safely as possible and expect to open the M-30 temporary bridge to traffic on Friday, March 12.
Photo: Crews have installed all bridge deck panels. Final paving will be scheduled when plants resume operations in the May.
0 Comments
Latest on Michimich.com
- Newborn Care Network Introduces Clinical Standard to Bridge the Six-Week Postpartum Gap
- The AAA Metamorphosis: How Global Gaming Is Redefining Production Standards
- Monexplora Explains the Options Mechanics Behind March's Tech Selloff and VIX Surge
- Larry R. Wasion Highlights Jump Gate I: Time Chair. The Opening Novel in His Expansive Science Fiction Series
- New Book Reveals The Science Of Predictions
- Compliance Alert: Maryland, Texas Regulate Use of Artificial Intelligence in Utilization Reviews
- Reozom Expands Flat Fee MLS Services in Florida and Michigan with Digital Listing Platform
- Colony Ridge Communities Celebrates Successful Soccer Season Kickoff with Families and Youth
- EFA Announces 2026 Editorial Rate Chart
- NYC Composer/Educator Launches Debut Children's Book to Fantastic Reviews
- Red5 Taps PubNub to Power the Next Era of Real-Time Interactive Streaming
- Shoutout Joseph Neibich aka Nybyk
- Meet Joseph Neibich aka Joseph Nybyk of Beachwood Canyon
- LARUS Launches Business Continuity Framework for IPv4-Dependent Networks
- KeysCaribbean Offers 'Skip-the-Crowds' Savings With 15 Percent Off April Stays
- Supply & Demand Chain Executive Names Puga Sankara as Recipient of 2026 Pros to Know Award
- Image Printing Company, Inc. Awarded GSA Multiple Award Schedule Contract, Expanding Federal Printing Capabilities
- Logicalis US Named to CRN's Tech Elite 250 for 2026
- AI Disruption Meets Marine Scale: Off The Hook YS, Inc. (N Y S E American: OTH) Targets Breakout Growth with NextBoat Launch and Aggressive Expansion
- Targeting the Billion-Dollar U.S. Countermeasure Market With AI-Driven Biodefense Platform: Lunai Bioworks (N A S D A Q: LNAI)