Michigan: Northbound I-75 lane closures at Carpenter Road for bridge maintenance in Genesee County start Oct. 28
Michimich.com/10033806

Contact: Jocelyn Hall, MDOT Office of Communications,  989-245-7117Agency: Transportation

COUNTY:
 Genesee

HIGHWAY:
 I-75

CLOSEST CITY:
 Flint

ESTIMATED DATE:
 Monday, Oct. 28, 2019

ESTIMATED COMPLETION DATE:
 Sunday, Nov. 3, 2019

PROJECT:
 The Michigan Department of Transportation (MDOT) will complete steel structural repairs to the Carpenter Road bridge over I-75. This work is part of an overall $1 million investment in structural repairs to 12 bridges across Genesee and Lapeer counties.

More on Michimich.com
Project map

TRAFFIC RESTRICTIONS:
 During daytime hours, northbound I-75 will have one lane closed. Motorists can expect two lanes closed overnight from 11 p.m. to 5 a.m. No lane closures will occur on Fridays and Saturdays in order to accommodate weekend travel.

This work is weather dependent.

SAFETY BENEFITS:
 This work involves repairing critical bridge components necessary to extend the life of the infrastructure.stats