Contact: Aaron Jenkins, MDOT Office of Communications, 517-243-9075 Agency: Transportation
COUNTY:
Jackson
HIGHWAYS:
Lansing Avenue
I-94
CLOSEST CITY:
Jackson
ESTIMATED START DATE:
6 a.m.
Tuesday, June 22, 2021
ESTIMATED COMPLETION DATE:
6 a.m.
Sunday, Nov. 14, 2021
OVERALL I-94 PROJECT COMPLETION DATE:
June 2023
PROJECT:
The Michigan Department of Transportation (MDOT) will close Lansing Avenue from Shirley Drive to Royal Drive to rebuild the bridge over I-94 in Jackson.
This work is part of MDOT's ongoing $120 million investment to rebuild and widen I-94 near the Airport Road interchange to just west of the east US-127/I-94 interchange in Blackman and Leoni Township. The I-94 project involves upgrading the US-127/M-50 (West Avenue)/I-94 interchange to a diverging diamond interchange, the Elm Road interchange with roundabouts, and rebuilding the Lansing Avenue bridge over I-94.
More on Michimich.com
Funding for this project is made possible by Gov. Gretchen Whitmer's Rebuilding Michigan program to rebuild the state highways and bridges that are critical to the state's economy and carry the most traffic. The investment strategy is aimed at fixes that result in longer useful lives and improves the condition of the state's infrastructure.
TRAFFIC RESTRICTIONS:
Southbound Lansing Avenue will be detoured east on Parnall Road, south on M-106 (Cooper Street), and then west on North Street back to Lansing Avenue.
Northbound Lansing Avenue will be detoured east on North Street, north on Cooper Street, and then west on Parnall Road back to Lansing Avenue.
Please follow posted detours. Motorists are advised to seek alternate routes.
SAFETY BENEFITS:
This traffic configuration will increase safety for workers and motorists through this work zone. These improvements will provide increased safety and mobility in this area of I-94, which is a significant local and national trade corridor.
COUNTY:
Jackson
HIGHWAYS:
Lansing Avenue
I-94
CLOSEST CITY:
Jackson
ESTIMATED START DATE:
6 a.m.
Tuesday, June 22, 2021
ESTIMATED COMPLETION DATE:
6 a.m.
Sunday, Nov. 14, 2021
OVERALL I-94 PROJECT COMPLETION DATE:
June 2023
PROJECT:
The Michigan Department of Transportation (MDOT) will close Lansing Avenue from Shirley Drive to Royal Drive to rebuild the bridge over I-94 in Jackson.
This work is part of MDOT's ongoing $120 million investment to rebuild and widen I-94 near the Airport Road interchange to just west of the east US-127/I-94 interchange in Blackman and Leoni Township. The I-94 project involves upgrading the US-127/M-50 (West Avenue)/I-94 interchange to a diverging diamond interchange, the Elm Road interchange with roundabouts, and rebuilding the Lansing Avenue bridge over I-94.
More on Michimich.com
- Detroit Puzzle Competition Concludes Final In-Person Round for $11,239 Prize
- IODefi Introduces New Web3 Infrastructure Framework as XRP Ledger Development Gains Global Attention
- Terizza Forms Strategic Collaboration with UC San Diego to Pioneer Next-Generation Distributed AI Infrastructure
- EnergyStrat Launches Global LNG Risk Outlook 2025–2030
- Strong Revenue Gains, Accelerating Growth, Strategic Hospital Expansion & Uplisting Advancements: Cardiff Lexington Corporation (Stock Symbol: CDIX)
Funding for this project is made possible by Gov. Gretchen Whitmer's Rebuilding Michigan program to rebuild the state highways and bridges that are critical to the state's economy and carry the most traffic. The investment strategy is aimed at fixes that result in longer useful lives and improves the condition of the state's infrastructure.
TRAFFIC RESTRICTIONS:
Southbound Lansing Avenue will be detoured east on Parnall Road, south on M-106 (Cooper Street), and then west on North Street back to Lansing Avenue.
Northbound Lansing Avenue will be detoured east on North Street, north on Cooper Street, and then west on Parnall Road back to Lansing Avenue.
Please follow posted detours. Motorists are advised to seek alternate routes.
SAFETY BENEFITS:
This traffic configuration will increase safety for workers and motorists through this work zone. These improvements will provide increased safety and mobility in this area of I-94, which is a significant local and national trade corridor.
0 Comments
Latest on Michimich.com
- UK Financial Ltd Announces It's Official Corporate Headquarters In The United Kingdom
- Rigani Press Announces Breakthrough Book for Health IT and Medical Leaders to Forge the Road to Responsible AI
- FreeTo.Chat - The bold, Anonymous Confession Platform, ushers in a new era of tension relief
- Female Founders Institute Announces Special Performance by Caitlin McGrath at the 2026 Charity Gala
- Hyatt House Fresno Celebrates Grand Opening, Introducing the First Hyatt House in Fresno, California
- "I Make Music Not Excuses" Journal by Anthony Clint Jr. Becomes International Amazon Best Seller, Empowering Music Creators Worldwide
- Novi Glass Company Says Why Custom Mirrors are Better
- Michigan Debt Collection Agency Helps Creditors Start the New Year Fresh!
- Ann Arbor Chiropractor Uses ESWT to Treat Elbow Pain
- Ann Arbor Computer Service Shares the Spirit of Giving!
- DanReDev, Kaufman Development & Oldivai Announce Major 2026 Projects Nationwide
- Accelerating Precious Metals Expansion and Digital Asset Innovation Ahead of 2026: Asia Broadband Inc. (Stock Symbol: AABB)
- Naturism Resurgence (NRE) Announces the World's First Standardised Stigma Measure (SSM) for Naturism
- London Art Exchange Emerges as a Leading Force in UK Contemporary Art, Elevating Three Artists to Secondary-Market Success
- myLAB Box Expands, Becoming the First and Only At-Home Testing Company to Serve the Entire Family—Human and Furry—with New Pet Intolerance Test
- Winning the C-Suite: How to Build the Executive Case for Sustained PLM Investment
- Entering 2026 with Expanding Footprint, Strong Industry Tailwinds, and Anticipated Q3 Results: Off The Hook YS Inc. (N Y S E American: OTH)
- Tiger-Rock Martial Arts Appoints Jami Bond as Vice President of Growth
- Super League (N A S D A Q: SLE) Enters Breakout Phase: New Partnerships, Zero Debt & $20 Million Growth Capital Position Company for 2026 Acceleration
- Finland's Gambling Reform Promises "Single-Click" Block for All Licensed Sites