FOR IMMEDIATE RELEASE June 30, 2020
Media Contact: Matt Helms 517-284-8300
Customer Assistance: 800-292-9555
Michigan.gov/MPSC
Twitter
The Michigan Public Service Commission today denied the relief Enbridge Energy LP sought in its request for a declaratory ruling and also rejected the company's request for ex parte approval of plans to relocate the Line 5 pipeline to a tunnel beneath the Straits of Mackinac. The Commission established a full hearing process for the proposal.
Enbridge in April filed an application (Case No. U-20763) requesting siting approval under Act 16 of 1929 to replace and relocate the Line 5 section in the Straits of Mackinac into a new tunnel it would build beneath the lakebed. In the alternative, Enbridge sought a declaratory ruling from the MPSC that the company already has authority from the Commission to build the replacement segment based on the MPSC's 1953 order that first granted permission for Line 5. The 645-mile interstate pipeline spans both Michigan peninsulas to transport light crude oil and natural gas liquids, including propane used for home heating in Michigan.
In today's order, the Commission found that, based on Enbridge's application and comments received from stakeholders, the Line 5 project differs substantially from the pipeline approved in 1953, and therefore the company does not have authority for the project under the 1953 order. Whereas the Commission approved in 1953 dual 20-inch pipelines constructed on the lakebed, Enbridge proposes replacing them with a single 30-inch pipeline housed in a concrete-lined tunnel 60-250 feet beneath the lakebed, involving a new easement and a 99-year lease of public trust property.
More on Michimich.com
The order states that Enbridge is required to file an Act 16 application, pursuant to Rule 447(1)(c) and Commission precedent, to obtain Commission approval to construct the Line 5 project through a contested case. The Commission found that the Line 5 project involves important factual, policy and legal issues best resolved through a proceeding that includes discovery, comprehensive testimony and evidence to provide a robust record. The Commission observed that this proposal is a matter of significant public interest best addressed through a contested case.
The Commission in April put Enbridge's application on hold while it considered the issue of a declaratory ruling and established a public comment period during which it sought public input specifically on any legal analysis of issues pertaining to Enbridge's request for a declaratory ruling. A number of stakeholders filed comments opposing Enbridge's request, including the Office of Attorney General Dana Nessel, more than a dozen Indian Tribes, a number of Michigan-based and national environmental organizations, and State Sen. Jeff Irwin. The Commission also received thousands of comments from Michigan residents, both in support of and in opposition to the tunnel project, many discussing the merits of Line 5 rather than focusing on the legal issues surrounding Enbridge's request for a declaratory ruling.
Following today's order, a notice of hearing will be issued with information on the scheduling of a prehearing conference and deadline for parties seeking to intervene in the formal contested case proceeding.
Opportunities to monitor and participate in MPSC's Line 5 proceedings
The MPSC is scheduling a public hearing on Aug. 24 to provide an overview of the MPSC process and Enbridge's application and for commissioners to hear directly from the public. The hearing will be held remotely with telephone and web access options. Additional details will be provided in the coming weeks.
The MPSC launched a dedicated webpage, www.michigan.gov/MPSCLine5, to enable the public to monitor Enbridge's siting application and related requests. Background resources on the MPSC's siting authority under Act 16 and opportunities for the public to participate are available. Individuals can sign up for e-mail updates on MPSC meeting notices, orders, press releases, public meetings, or other developments specifically related to the Line 5 proceeding before the Commission. Instructions are also available for individuals seeking to sign up to be notified of all formal case filings through the MPSC's e-dockets system. Additional information will be posted on the website as it becomes available.
More on Michimich.com
MPSC ISSUES SHOW CAUSE ORDER TO CYNERGYCOMM.NET IN DISCONTINUANCE OF SERVICE CASE
The MPSC today ordered CynergyComm.net, Inc., to show cause why it should not be held in violation of the Michigan Telecommunications Act's requirements for proper notification of its intent to discontinue service. The MPSC has received several complaints from CynergyComm customers about notifications they received saying the company intended to terminate service, despite warnings issued to the company that it must follow state and federal laws governing discontinuance of service. MPSC Staff on June 22 notified CynergyComm that it must provide the Commission with evidence that federal and state notice requirements have been filed by June 29; as of this order, no such paperwork has been received. The Commission today ordered CynergyComm to file a response in this docket by 5 p.m. July 9, 2020, and to appear with counsel at a prehearing conference scheduled for 11 a.m. July 16.
To look up cases from today's meeting, access the E-Dockets filing system here.
To watch recordings of the MPSC's meetings, click here.
For information about the MPSC, visit www.Michigan.gov/MPSC, sign up for one of its listservs, or follow the Commission on Twitter.
DISCLAIMER: This document was prepared to aid the public's understanding of certain matters before the Commission and is not intended to modify, supplement, or be a substitute for the Commission's orders. The Commission's orders are the official action of the Commission.
Media Contact: Matt Helms 517-284-8300
Customer Assistance: 800-292-9555
Michigan.gov/MPSC
The Michigan Public Service Commission today denied the relief Enbridge Energy LP sought in its request for a declaratory ruling and also rejected the company's request for ex parte approval of plans to relocate the Line 5 pipeline to a tunnel beneath the Straits of Mackinac. The Commission established a full hearing process for the proposal.
Enbridge in April filed an application (Case No. U-20763) requesting siting approval under Act 16 of 1929 to replace and relocate the Line 5 section in the Straits of Mackinac into a new tunnel it would build beneath the lakebed. In the alternative, Enbridge sought a declaratory ruling from the MPSC that the company already has authority from the Commission to build the replacement segment based on the MPSC's 1953 order that first granted permission for Line 5. The 645-mile interstate pipeline spans both Michigan peninsulas to transport light crude oil and natural gas liquids, including propane used for home heating in Michigan.
In today's order, the Commission found that, based on Enbridge's application and comments received from stakeholders, the Line 5 project differs substantially from the pipeline approved in 1953, and therefore the company does not have authority for the project under the 1953 order. Whereas the Commission approved in 1953 dual 20-inch pipelines constructed on the lakebed, Enbridge proposes replacing them with a single 30-inch pipeline housed in a concrete-lined tunnel 60-250 feet beneath the lakebed, involving a new easement and a 99-year lease of public trust property.
More on Michimich.com
- Keyanb Exchange Implements Enhanced Security Protocols Amid Industry-Wide Trust Challenges
- TSWHZC Platform Combines Automated Portfolio Management with Proof of Reserves for Brazil Market Entry
- AureaVault Positions Digital Asset Infrastructure for Shifting Monetary Policy Environment
- JQRBT Unveils High-Speed Trading Infrastructure Designed for Growing Institutional Crypto Market
- New Leadership and Renovations Usher in Next Chapter for Sunrise Manor
The order states that Enbridge is required to file an Act 16 application, pursuant to Rule 447(1)(c) and Commission precedent, to obtain Commission approval to construct the Line 5 project through a contested case. The Commission found that the Line 5 project involves important factual, policy and legal issues best resolved through a proceeding that includes discovery, comprehensive testimony and evidence to provide a robust record. The Commission observed that this proposal is a matter of significant public interest best addressed through a contested case.
The Commission in April put Enbridge's application on hold while it considered the issue of a declaratory ruling and established a public comment period during which it sought public input specifically on any legal analysis of issues pertaining to Enbridge's request for a declaratory ruling. A number of stakeholders filed comments opposing Enbridge's request, including the Office of Attorney General Dana Nessel, more than a dozen Indian Tribes, a number of Michigan-based and national environmental organizations, and State Sen. Jeff Irwin. The Commission also received thousands of comments from Michigan residents, both in support of and in opposition to the tunnel project, many discussing the merits of Line 5 rather than focusing on the legal issues surrounding Enbridge's request for a declaratory ruling.
Following today's order, a notice of hearing will be issued with information on the scheduling of a prehearing conference and deadline for parties seeking to intervene in the formal contested case proceeding.
Opportunities to monitor and participate in MPSC's Line 5 proceedings
The MPSC is scheduling a public hearing on Aug. 24 to provide an overview of the MPSC process and Enbridge's application and for commissioners to hear directly from the public. The hearing will be held remotely with telephone and web access options. Additional details will be provided in the coming weeks.
The MPSC launched a dedicated webpage, www.michigan.gov/MPSCLine5, to enable the public to monitor Enbridge's siting application and related requests. Background resources on the MPSC's siting authority under Act 16 and opportunities for the public to participate are available. Individuals can sign up for e-mail updates on MPSC meeting notices, orders, press releases, public meetings, or other developments specifically related to the Line 5 proceeding before the Commission. Instructions are also available for individuals seeking to sign up to be notified of all formal case filings through the MPSC's e-dockets system. Additional information will be posted on the website as it becomes available.
More on Michimich.com
- Who Will Win the 2025 WNBA Finals? OddsTrader Shares Live Betting Odds and Projections
- Geeks5g Creative Marketing: The Powerhouse Behind Business Growth
- Two new inductees selected to the Trenton Educational Foundation's Wall of Fame
- Agemin Unveils Breakthrough AI Model for Biometric Age Estimation, Setting New Standards in Online Child Safety
- Strategic Partnerships with Defiant Space Corp and Emtel Energy USA Powerfully Enhance Solar Tech Leader with NASA Agreements: Ascent Solar $ASTI
MPSC ISSUES SHOW CAUSE ORDER TO CYNERGYCOMM.NET IN DISCONTINUANCE OF SERVICE CASE
The MPSC today ordered CynergyComm.net, Inc., to show cause why it should not be held in violation of the Michigan Telecommunications Act's requirements for proper notification of its intent to discontinue service. The MPSC has received several complaints from CynergyComm customers about notifications they received saying the company intended to terminate service, despite warnings issued to the company that it must follow state and federal laws governing discontinuance of service. MPSC Staff on June 22 notified CynergyComm that it must provide the Commission with evidence that federal and state notice requirements have been filed by June 29; as of this order, no such paperwork has been received. The Commission today ordered CynergyComm to file a response in this docket by 5 p.m. July 9, 2020, and to appear with counsel at a prehearing conference scheduled for 11 a.m. July 16.
To look up cases from today's meeting, access the E-Dockets filing system here.
To watch recordings of the MPSC's meetings, click here.
For information about the MPSC, visit www.Michigan.gov/MPSC, sign up for one of its listservs, or follow the Commission on Twitter.
DISCLAIMER: This document was prepared to aid the public's understanding of certain matters before the Commission and is not intended to modify, supplement, or be a substitute for the Commission's orders. The Commission's orders are the official action of the Commission.
0 Comments
Latest on Michimich.com
- Tour Napa Like a Local: Vines of Napa Valley Wine Passport AKA Vine Pass Unlocks Hidden Gems
- Dental Surgical Center Accepts Sedation Patients with Medicaid for MD, WV, PA and DC
- Sloan's Lake Dental Launches New Website to Enhance Patient Experience and Access to Modern Dental Care
- Only 3 Weeks Left till the Start of the OpenSSL Conference 2025
- Comerica Incorporated Names Kristina Janssens Senior Executive Vice President and Chief Risk Officer
- ENTOUCH Completes $50 million Funding Round
- Teaming Agreement with Emtel Energy USA to Advance Thin-Film PV Energy Storage Capabilities; NASA agreements for Solar Space Tech; Ascent Solar $ASTI
- Nebuvex Acknowledges Platform "Too Secure" for Anonymous Traders; Institutional Investors Disagree
- From Tokyo to Berlin: FreeTo.Chat Unites Cultures with the World's First Confession VRX — EmojiStream™
- AZETHIO Launches Multi-Million Dollar User Protection Initiative Following Unprecedented Platform Growth
- Matecrypt Observes South American Cryptocurrency Adoption Surge Amid Economic Shifts
- Assent Uncovers Over 695 Unique PFAS Across Global Supply Chains as Regulations Increase
- Cryptocurrency Quarterly Trading Volume Surpasses $15 Trillion Record High as BrazilNex Acknowledges Industry 'Growing Pains' Amid Market Speculation
- AHRFD Initiates Legal Proceedings Against Anwalt.de for Publishing Defamatory and False Content
- New Analysis Reveals the Complex Forces Driving the 'Great Human Reshuffle'
- Elevate Unveils GroundComm X30 at 2025 International GSE Expo in Las Vegas
- NEW power supply release from Kepco Dynatronix - HSP Advanced
- St. Augustine Honors Hispanic Heritage Month
- Vesica Health Receives AUA Guideline Inclusion
- Steward's Plumbing Sponsors the 2025 Samson Challenge, Bringing Community, Fitness, and Fun Together in Albuquerque